Guide

Timber frame estimating and design software: what to use for pricing, design and production

Published · Updated · 10 min read · By Tony Huaulmé

In short

Timber frame software is any tool that turns a plan into quantities, drawings or machine data for a timber frame job, from a spreadsheet to timber CAD/CAM. No single tool covers every stage, so pick by what you're doing: for pricing, a spreadsheet, a PDF takeoff tool or an AI agent that starts from the plan you receive save you redrawing a job you haven't won yet; for design and production, timber CAD/CAM and BIM software (hsbcad, cadwork, SEMA, Dietrich's, Vertex BD, StrucSoft) produce drawings, lists and machine data. The deciding figure is the take-off hours you spend on jobs you don't win.

Looking for timber frame software usually means mixing up three needs: pricing a job, designing it, then building it. The tools don't all sit at the same stage, and the biggest drain on time isn't always where you'd expect: it's the take-off on a job that never goes ahead. Here are the four kinds of tools, sorted by stage, a comparison table and a worked example to calculate your own hours.

Pricing, design, production: which software for which stage?

A timber frame house job goes through three stages, and each one asks something different of the software:

One tool can cover several stages, but rarely at the same cost in time. The classic trap is redrawing a whole project just to price it, when part of the jobs you price will never be built. The real cost of software isn't only the licence: it's the hours spent building a model for a job you lose.

Is a spreadsheet enough to price a timber frame?

For a few simple walls, yes. One row per wall, the stud count rule (length / stud spacing, rounded up, + 1), the opening framing, one tab per section: a spreadsheet costs nothing extra, it's flexible, and you know every formula in it. The full counting method is in our timber frame wall take-off guide.

It runs out of road quickly:

Timber frame CAD/CAM and BIM software: hsbcad, cadwork, Vertex BD, StrucSoft and others

These are the trade's design and production tools. What they have in common: the take-off comes from a 3D model you build in the software, and that model then produces drawings, lists and machine data. Here is what each vendor says on its own site:

For design and production, these tools produce what the shop needs. For pricing, the question is different: how many hours does it take to redraw the project before the first take-off, and how many of those projects will you win?

PDF takeoff software: measuring the drawing, with no frame behind it

Another family of tools works directly on the plan you receive: you open the PDF or image, set the scale against a known dimension, then trace lengths, areas and counts. PlanSwift, for instance, describes itself as takeoff and estimating software where you measure by pointing and clicking on PDF, CAD and image files. It's quick for wall lengths and elevation areas, and the tool keeps a record of what was measured on the drawing.

But these tools measure the drawing, not the building. They don't know what a stud, a lintel (header) or a plate is: the stud count, the opening framing and the timber volume still have to be worked out, usually in a spreadsheet alongside. And none of that work feeds the shop once the job is won.

Starting from the plan you receive: an AI agent that builds the model for you

The last category is newer: an AI agent reads the plan you receive and builds the 3D model of the building itself, without you redrawing it. You talk to it in a chat ("2.50 m walls, timber frame") and you correct anything that's wrong by typing it.

A dimensioned 2D plan of a 12 × 8 m house on the left, and the same house as a 3D timber frame on the right
From the dimensioned plan you receive to a 3D timber frame, with no redrawing (illustration).

That's where Stud sits. It takes a DXF or PDF plan, a plan image or a dimensioned sketch, builds the storeys, walls, openings, floors and flat roofs, and, when a dimension is missing, uses a standard value and flags it for you. The take-off comes from the model: wall, floor and roof areas, timber volume and weight. Once the job is won, it splits the walls into panels and draws the frame (studs, plates, lintels, joists) from the same model.

Its limits, worth knowing before you choose:

Clean, well-dimensioned plans give the best results; a blurry scan or a plan with few dimensions will mean more questions.

If you are weighing timber against steel, Stud's comparison of light gauge steel vs timber frame panels covers what changes for a prefab builder, including the tools each material calls for.

Timber frame estimating software compared, by type of tool

This table doesn't score the tools: it says what each type needs to start and what it leaves for the shop.

Type of toolWhat you give itTime to the first take-offWhat feeds the shop afterwards
SpreadsheetDimensions read off the plan, typed in by handShort on a simple wall, grows with the number of walls and openingsA list of quantities, with no member positions: the frame still has to be drawn
Timber CAD/CAM and BIM (hsbcad, cadwork, Vertex BD, StrucSoft, SEMA, Dietrich's)The project redrawn in the software, with a PDF or IFC as a base in some toolsThe time it takes to redraw the projectThe model: drawings, lists, machine data depending on the modules
PDF takeoffThe plan as a PDF or image, scaledThe time to set the scale and trace the measurementsLengths and areas, with no frame or members
AI agent from the plan (Stud)The plan you received (DXF, PDF, plan image, dimensioned sketch) and your instructions in a chatThe time for the agent to build the model and for you to answer its questionsThe same model, split into panels with its frame; exports with the Framer plan

The types combine: plenty of shops price with one tool and build with another. What matters is not doing the same work twice, or at least doing it twice knowingly.

Worked example: how many take-off hours a month?

Example

The figures below (number of jobs, win rate, hours per job) are example values to show the calculation: replace them with your own. We count in hours, not money: multiply by your own hourly rate afterwards if you want to.

Assumptions. You price 12 jobs a month and win one in four (a 25% win rate): 3 jobs won, 9 lost. Two ways of working:

ItemA: all in timber CADB: spreadsheet, then timber CAD
Take-off on the 12 jobs priced12 × 6 = 72 h12 × 2.5 = 30 h
Redrawing the 3 jobs won0 h3 × 6 = 18 h
Total per month72 h48 h
Of which hours on the 9 jobs lost9 × 6 = 54 h9 × 2.5 = 22.5 h
Take-off hours per job won72 / 3 = 24 h48 / 3 = 16 h

In A, 54 of the 72 hours, or 75% of the take-off time, go on jobs that will never be built. In B, the total drops, but the jobs you win are taken off twice, and the quantities on the quote don't come from the model the shop uses: any gap between the two only shows up in production.

The formula to keep: hours lost per month = jobs priced × (1 − win rate) × take-off hours per job. Here: 12 × 0.75 × 6 = 54 h. That's the line a pricing tool has to bring down, without making you start again when you win the job.

How to choose timber frame software for your volume of quotes

Before you compare features, measure your own situation:

  1. Count the jobs you price each month and your win rate over the last six months.
  2. Time the take-off on three recent jobs, from the plan received to the quantities, with your current tool.
  3. Work out your hours lost with the formula from the example.
  4. Look at what happens when you win a job: does the take-off from the quote feed the shop, or is everything redrawn?
  5. Test each tool on a plan you've already taken off: compare the timber volume and areas with your own figures, and note the time spent.

A few pointers for reading the result:

For the pricing method itself, from the drawings to a price, see our guide on how to price a timber frame house from plans.

3D view of a house's timber frame in Stud: stud walls, openings and flat roof joists
A house's timber frame, drawn in Stud from the plan (illustration).

Frequently asked questions

What is the best timber frame design software?

There isn't one for every stage. Timber CAD/CAM software is built for design and production; for pricing, the right tool is the one that gives you an accurate take-off without redrawing the jobs you won't win.

Is there free timber frame estimating software?

A spreadsheet handles the take-off of a simple wall at no extra cost. Stud is in a free beta, with 200 free credits and no card required; the beta does everything in the app, with no export. For timber CAD/CAM software, check with the vendor directly.

Does take-off software price the house?

A take-off gives you quantities; the price comes from your buying prices, labour ratios and mark-up. Stud doesn't calculate prices. Some timber CAD software exports its lists to a quoting tool.

Does the software check the structure against building codes?

Stud does no structural design and no code checking. Sections, stud spacing and long-span lintels (headers) must be checked by your structural engineer.

Test it with Stud, on a plan you've already priced

Stud is an AI agent that sits at the pricing stage: it starts from the plan you receive, with no redrawing:

  • you attach a DXF or PDF plan, a plan image or a dimensioned sketch to the chat, with your instructions (wall height, timber frame);
  • the agent builds the building in 3D and, when a dimension is missing, uses a standard value and flags it for you;
  • it gives you the take-off: wall, floor and roof areas, timber volume and weight;
  • once you win the job, it splits the walls into panels and draws the timber frame from the same model, at the stud spacing and maximum panel width you set.

Stud doesn't calculate prices and doesn't do structural design. The free beta does everything in the app, with no export; IFC, production PDFs and machine files (for light steel framing machines) come with the Framer plan.

Try the beta for free

200 free credits, no card required. Upload a plan you've already taken off and compare the timber volume.