Timber frame flat roof: joists, falls and take-off from a 2D plan
In short
A timber frame flat roof is taken off like a floor that has to drain. Joists = length across the joists / joist spacing, rounded up, + 1, per span, plus rim joists and blocking. The falls come from firrings on the joists (or tapered insulation): one firring per joist, its depth set by the fall and the run. The deck, insulation and vapour control layer follow the roof area; the membrane adds its upstands and laps. The plan rarely gives the fall, the build-up or the kerb height: find them before you count.
With a pitched roof on trusses, the truss supplier designs the roof and you count trusses. A timber frame flat roof is different: the joists, the firrings and the deck are yours to take off, and the plan view is, for once, almost the real area. Here is the method, then the 10 × 8 m house of our take-off guide, with a flat roof this time instead of a gable roof on trusses.
Flat roof take-off from plans: what is drawn, what is missing?
A flat roof shows up on the plans as a roof plan with a few arrows, outlets and a parapet or kerb line, and as one line in the sections. What the take-off needs is mostly in the sections and the specification, when it is anywhere.
| What you need | Where it usually is | If it's not there |
|---|---|---|
| Joist direction and spans | Structural drawing, section | Usually the short way, onto load-bearing walls or a beam: ask, or state it |
| Joist section and spacing | Structural drawing | Your engineer's call, not the take-off's |
| Falls and their direction | Roof plan (arrows, outlets, gutters) | Ask: the fall decides the firrings or the tapered insulation |
| Build-up (deck, insulation, membrane) | Section, specification | Ask, or write a warm-roof assumption on the take-off |
| Parapets, kerbs, upstand heights | Section, details | Ask: they add membrane area and timber |
Write down every value you didn't read on the drawings, as in our whole-house take-off guide: an assumption on the take-off is a question you can send to the client. The minimum fall in particular isn't yours to pick: it comes from the membrane manufacturer and the rules where you build.
How many joists, and at what spacing?
The roof joists are counted like a floor, span by span:
- Joists per span = length of the roof across the joists / joist spacing, rounded up, + 1.
- Spans: on a central beam or an internal load-bearing wall, each position takes two joists, one per span.
- Joist length = span from the rim joist to the bearing line, minus the rim joist thickness, then rounded up to stock length. Add any overhang at the eaves.
- Rim joists along the ends of the joists, on both sides.
- Blocking over the central bearing, and noggings where your detail asks for them.
- Trimmers round a rooflight or a hatch: doubled joists each side, a trimmer across each end.
Flat roof joist spacing is usually 400 or 600 mm (16 or 24 in. on centre in the US). Closer joists take a thinner deck and a shallower section for the same span; wider ones mean fewer joists and fewer firrings, but a thicker deck. The section and the spacing are your engineer's, with the deck and the loads (snow, access, a green roof) in mind. Our guide on 400 vs 600 mm stud spacing runs the same trade-off for walls.
How do you get the falls: firrings or tapered insulation?
A flat roof is never flat: it falls to a gutter or an outlet. In a timber frame roof, there are two common ways to make the fall:
- firrings: tapered timber strips nailed along the top of each joist, deep at the high end and thin at the low end. The joists stay level, the deck follows the firrings. When the fall runs along the joists, it's one firring per joist, as long as the joist;
- tapered insulation on a level deck: the insulation boards are cut to the fall, and the timber take-off stops at the deck. The fall then belongs to the insulation supplier's layout.
For firrings, the depth difference = run / fall ratio: at 1:60 over a 3.955 m joist, 3,955 / 60 = 66 mm. Keep a minimum depth at the low end (14 mm below) so the strip can be nailed without splitting. When the fall runs across the joists instead, the firrings become cross-battens of different depths, one per row: count them per row, not per joist.
Open web joists on a flat roof: when?
Open-web joists (timber flanges joined by pressed steel webs, sometimes called metal-web joists) take longer spans than solid joists of the same depth, and services run through the webs. On the example house, they could often clear the 8.00 m in one span, with no central beam: 26 joists instead of 52, but deeper ones. Like trusses, they are designed and supplied by the manufacturer from its span tables: what you take off is the number of positions, the span, the spacing, the depth and the end details, then you check the supplier's quote against it.
On a light gauge steel building, the equivalent is a steel open-web joist (a lattice girder rolled from cold-formed steel). Stud's page on light gauge steel framing shows that version.
Example: the 10 × 8 m house with a flat roof
The single-storey house of our 2D plan take-off guide, 10.00 × 8.00 m to the outside of the frame, same walls, with a flat roof instead of the gable roof on trusses. Roof joists 45 × 220 at 400 mm across the 8.00 m width, in two 4.00 m spans over a central beam (not counted here). Firrings 45 mm wide, design fall 1:60 from the central beam to a gutter along each 10 m wall. Warm roof: 18 mm deck, vapour control layer, insulation, membrane. A kerb on the two 8 m sides, membrane turned up 150 mm. Example values to illustrate the method.
Joists. Positions along the 10.00 m: 10.00 / 0.40 = 25, + 1 = 26. Two spans: 52 joists at 3.955 m (4.00 m less the 45 mm rim joist), 205.66 m. Rim joists: 2 × 10.00 m. Blocking over the central beam: one row of 25 pieces at 0.355 m, 8.88 m.
Firrings. One per joist: 52 firrings of 3.955 m, 80 mm deep at the beam, 14 mm at the gutter (66 mm of fall at 1:60), 45 mm wide.
Areas. Deck, vapour control layer and insulation: 80.00 m² (at 1:60, the slope adds less than 0.1%). Membrane: 80.00 m² + 2 × 8.00 × 0.15 m of upstand = 82.40 m², before the laps your membrane needs. Edges: 20.00 m of gutter edge, 16.00 m of kerb.
| Item | Section | Qty | Total | m³ |
|---|---|---|---|---|
| Roof joists, rim joists, blocking | 45 × 220 | 79 | 234.54 m | 2.322 |
| Firrings, 80 → 14 mm | 45 wide | 52 | 205.66 m | 0.435 |
| Total | Roof timber | 2.757 | ||
| Deck, vapour control layer, insulation | 80.00 m² | |||
| Membrane, with upstands | 82.40 m² |
Volume and weight. 2.76 m³ of roof timber net, about 1,160 kg in C24 (mean density 420 kg/m³). With 10% waste: 3.03 m³ to order.
Against the gable roof. The same house on trusses took 18 trusses from the supplier and 113.87 m² of roof covering. With the flat roof, you take off 52 joists and 52 firrings yourself, and the roof area drops to 80.00 m² of deck: the plan view is right this time, the upstands are what you add.
Common mistakes
- Counting one joist per position when the roof has two spans over a beam.
- Forgetting the firrings, or counting them per joist when the fall runs across the joists.
- Taking the fall from the drawing when nobody wrote it: the minimum fall comes from the membrane manufacturer and the rules that apply.
- Leaving out the upstands: kerbs and parapets add membrane area, and timber for the kerbs.
- Mixing the deck area and the membrane area: the membrane adds upstands and laps.
- Pricing open-web joists like solid ones: they come from the manufacturer's design, with their own depth and end details.
The flat roof is also where the timber frame meets the steel world: the same building in light gauge steel is framed on steel joists or lattice girders. Stud's timber frame page shows what the agent builds in timber, from walls to roof.
Related guides
Stud spacing 400 vs 600 mm (16 vs 24 in. o.c.): what it does to the take-offHow many extra studs, m³ and kg at 400 mm centres, and what the stud size adds. The 8 m wall recounted piece by piece.
Timber frame window opening: lintel, jack studs and sill in a wallKing and jack studs, lintel, sill, short studs and blocking: how to count and cut them, with a worked example.
Timber frame cutting list: from the framing to the pieces to cutColumns, grouping by panel and by section, stock lengths and offcuts, with a worked 8 m wall.